Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact.
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a claude-codeProject install by default; add -g for ~/.claude/skills/.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writer --agent claude-codeProject scope by default; add --scope user for a personal install. Needs GitHub CLI 2.90.0 or later (public preview).
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .claude/skills && cp -r skills-src/skills/change-order-writer .claude/skills/change-order-writer && rm -rf skills-srcUse ~/.claude/skills/ instead of .claude/skills for a personal install. The folder must contain SKILL.md.
Claude Code skills documentation · loads skills from .claude/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .claude/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.Claude Code copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
$skill-installer install https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writerType this inside Codex. $skill-installer <name> installs a curated skill from openai/skills. The installer writes to $CODEX_HOME/skills (default ~/.codex/skills). Restart Codex if the skill does not show up.
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a codexProject install goes to .agents/skills/; add -g for ~/.codex/skills/.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writer --agent codexProject scope by default (.agents/skills/); add --scope user for a personal install.
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .agents/skills && cp -r skills-src/skills/change-order-writer .agents/skills/change-order-writer && rm -rf skills-srcUse ~/.agents/skills/ instead of .agents/skills for a personal install.
Codex skills documentation · loads skills from .agents/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .agents/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.Codex copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a cursorProject install goes to .agents/skills/; add -g for ~/.cursor/skills/.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writer --agent cursorProject scope by default (.agents/skills/); add --scope user for a personal install.
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .cursor/skills && cp -r skills-src/skills/change-order-writer .cursor/skills/change-order-writer && rm -rf skills-srcUse ~/.cursor/skills/ instead of .cursor/skills for a personal install.
Cursor skills documentation · loads skills from .cursor/skills/, .agents/skills/, .claude/skills/, .codex/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .cursor/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.Cursor copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
$ gemini skills install https://github.com/mohitagw15856/pm-claude-skills.git --path skills/change-order-writer--scope user (default) or --scope workspace; --path is the subfolder of the repo that holds the skill; --consent skips the security confirmation prompt.
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a gemini-cliProject install goes to .agents/skills/; add -g for ~/.gemini/skills/.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writer --agent gemini-cliProject scope by default (.agents/skills/); add --scope user for a personal install.
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .gemini/skills && cp -r skills-src/skills/change-order-writer .gemini/skills/change-order-writer && rm -rf skills-srcUse ~/.gemini/skills/ instead of .gemini/skills for a personal install, then run /skills reload.
Gemini CLI skills documentation · loads skills from .gemini/skills/, .agents/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .gemini/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.Gemini CLI copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writerInstalls for Copilot at project scope by default; add --scope user for a personal install. Preview a skill first with gh skill preview. Needs GitHub CLI 2.90.0 or later (public preview).
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a github-copilotProject install goes to .agents/skills/; add -g for ~/.copilot/skills/.
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .github/skills && cp -r skills-src/skills/change-order-writer .github/skills/change-order-writer && rm -rf skills-srcUse ~/.copilot/skills/ instead of .github/skills for a personal install. Commit .github/skills so cloud agent and code review can use it.
GitHub Copilot skills documentation · loads skills from .github/skills/, .claude/skills/, .agents/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .github/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.GitHub Copilot copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
$ npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a opencodeOpenCode documents no install command of its own. Project install goes to .agents/skills/; add -g for ~/.config/opencode/skills/.
$ gh skill install mohitagw15856/pm-claude-skills change-order-writer --agent opencodeProject scope by default (.agents/skills/); add --scope user for a personal install.
$ git clone --depth 1 https://github.com/mohitagw15856/pm-claude-skills.git skills-src && mkdir -p .opencode/skills && cp -r skills-src/skills/change-order-writer .opencode/skills/change-order-writer && rm -rf skills-srcUse ~/.config/opencode/skills/ instead of .opencode/skills for a personal install.
OpenCode skills documentation · loads skills from .opencode/skills/, .claude/skills/, .agents/skills/
Install the "change-order-writer" agent skill from https://github.com/mohitagw15856/pm-claude-skills/tree/main/skills/change-order-writer into .opencode/skills/change-order-writer/ in this project. Copy the whole folder (SKILL.md and every file beside it), keep the folder name "change-order-writer", then confirm the skill loads.OpenCode copies the folder itself, the same result as the manual copy. Check what it changed before you commit it.
change-order-writerDraft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact.
Change Order Writer is an agent skill from mohitagw15856/pm-claude-skills. Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact. Use when asked to write a change order, price extra work, draft a CO or COR/PCO, respond to a directive for changed work, or paper a field change. Produces a complete change order request with contract-clause entitlement, labour/material/equipment/OH&P breakdown, time impact statement, and reservation of rights.
Its SKILL.md is about 1.5k tokens, which your agent loads only when the skill is triggered. It is a single SKILL.md file with no bundled scripts.
The repository describes itself as: 1255 professional Agent Skills for Claude, ChatGPT, Gemini, Cursor & Codex — PRDs, postmortems, leases, medical bills, layoffs, go-bags, new countries. Plain markdown, MIT, in… The licence is MIT.
Read from SKILL.md and the folder at commit 1cbf1f0. It shows what the files ask for, not the result of running them.
Pre-approves nothing: there is no allowed-tools line, so your agent's usual permission prompts apply.
From allowed-tools in the SKILL.md frontmatter.
No scripts in the folder and no shell commands in SKILL.md.
From the folder's file list and the shell code blocks in SKILL.md.
No URLs in SKILL.md.
From URLs in SKILL.md, links to its own repository left out.
Names no API keys, tokens, secrets or passwords.
From names ending in _API_KEY, _TOKEN, _SECRET, _KEY or _PASSWORD in SKILL.md.
Change Order Writer loads about 1.5k tokens when it runs. Until then it costs about 114 tokens; SKILL.md has 736 words of instructions outside code blocks.
Estimates: characters ÷ 4, the usual rule of thumb; real counts depend on the model's tokenizer. Scripts and assets cost tokens only if the agent reads them.
The automated check found no risky patterns in SKILL.md.
Automated static check — not a guarantee. Review scripts before installing. It scans the text of SKILL.md for risky patterns (piping downloads into a shell, reading credential files, hidden Unicode, destructive commands); files beside SKILL.md are not scanned.
The full file from mohitagw15856/pm-claude-skills at commit 1cbf1f0, republished under its MIT licence (© mohitagw15856). 736 words, ~1,473 tokens.
.claude/skills/change-order-writer/SKILL.md (or your agent's skills folder).A change order that just says "extra work — $48,500" gets cut in half in review. A defensible one answers three questions before they're asked: why am I entitled (which contract clause, triggered by what event), what exactly changed (scope delta from the contract baseline), and what does it really cost (built-up pricing plus time). This skill drafts change orders that survive an owner's rep audit — and preserves rights on the impacts you can't price yet.
Ask for what's missing; from a thin brief, draft anyway and mark every gap [confirm]:
Entitlement first. Classify the trigger — it drives the clause you cite:
| Trigger | Typical basis |
|---|---|
| Owner/architect directive or design revision | Changes clause (e.g. AIA A201 §7 / EJCDC / contract equivalent) |
| Differing site condition | DSC clause — Type I (differs from documents) or Type II (unusual for the locality) |
| RFI answer adding work | Changes clause via the RFI/ASI as the directive document |
| Owner-caused delay/interference | Changes + delay provisions (pair with a delay notice) |
Never assert entitlement without naming the clause and the triggering document by number and date. If notice deadlines have passed, say so and frame the submission accordingly — don't hide it.
Pricing build-up. Price from records, not round numbers: labour (crew × hours × loaded rates — base plus burden), material (quantities × quoted prices, attach quotes), equipment (owned at established rates, rented at invoice), subcontractor cost, then apply OH&P at the contract-specified markups on self-performed and sub work separately. Include small-tools/consumables, supervision, and bond/insurance adjustment if the contract allows. Anything estimated rather than quoted gets labelled.
Time. State added work duration and whether it hits the critical path. If time impact can't be fixed yet, request a to-be-determined extension and reserve rights — never write "no schedule impact" as a default.
Project / Contract No. / Date / To / From 1. Description of change — plain-language summary of the changed condition. 2. Entitlement — clause citation + triggering document (RFI #, ASI #, directive, DSC discovery date) + notice given (date, method). 3. Scope delta — was/is table against contract documents. 4. Pricing — itemised table: Labour / Material / Equipment / Subcontractors / Subtotal / OH&P (per §[x]) / Bond & insurance / Total. Attachments list (quotes, tickets, T&M sheets). 5. Schedule impact — [X] calendar days requested, critical-path basis stated, or expressly reserved pending analysis. 6. Reservation of rights — rights reserved for cumulative impact, acceleration, and consequential effects not quantifiable at submission. 7. Signature block and the line: "This draft is not legal advice — route through your contracts counsel before sending."
[confirm]© mohitagw15856, MIT. Rendered from Markdown: HTML in the file is shown as text, images as links, and headings moved down two levels. Raw file
Just SKILL.md in skills/change-order-writer of mohitagw15856/pm-claude-skills.
Open the folder on GitHubat commit 1cbf1f0
Change Order Writer next to the 5 skills that share the most tags, products or categories with it. Stars are the repository's; “used in” counts other GitHub owners with a copy.
| Skill | Stars | Used in | Tokens | Auto-check | Licence | Repo updated |
|---|---|---|---|---|---|---|
| Change Order Writer this skillmohitagw15856/pm-claude-skills | 1.4k | — | ~1.5k | Automated safety check: Pass | MIT | |
| Higher Order Article Writerdigoal/blog | 8.6k | — | ~1.7k | Automated safety check: Pass | GPL-2.0 | |
| CSS Orderthedaviddias/Front-End-Checklist | 74k | — | ~404 | Automated safety check: Pass | MIT | |
| Focus Orderthedaviddias/Front-End-Checklist | 74k | — | ~519 | Automated safety check: Pass | MIT | |
| Heading Orderthedaviddias/Front-End-Checklist | 74k | — | ~452 | Automated safety check: Pass | MIT | |
| Food Orderingasgeirtj/system_prompts_leaks | 69k | — | ~1.4k | Automated safety check: Pass | CC0-1.0 |
digoal/blog
Read a provided URL, local file, or pasted article, digest its core claims and assumptions, rebuild the topic into a concise original source-backed Chinese Markdown article, and save it under the…
thedaviddias/Front-End-Checklist
A skill your agent uses when reviewing stylesheets, component styles, and responsive behavior related to Order CSS files correctly.
thedaviddias/Front-End-Checklist
A skill your agent uses when reviewing rendered HTML, interactive components, or design-system patterns related to Ensure logical focus order.
thedaviddias/Front-End-Checklist
A skill your agent uses when reviewing rendered HTML, interactive components, or design-system patterns related to Maintain logical heading order.
asgeirtj/system_prompts_leaks
Prepare restaurant food orders for delivery or pickup; use for cart, checkout and tracking.
sickn33/agentic-awesome-skills
Defend AI systems against prompt injection and indirect prompt attacks using input controls, tool permissions, output validation, and isolation boundaries.
mohitagw15856/pm-claude-skills
Compare the total cost of car ownership across buy-new, buy-used, lease, and keep-your-current-car — depreciation, insurance, maintenance ramp, and fuel over a real horizon, not just the monthly…
mohitagw15856/pm-claude-skills
Build a customer health scorecard for a specific account. An agent skill from mohitagw15856/pm-claude-skills.
mohitagw15856/pm-claude-skills
Compute who gets what at each exit price from a cap table — liquidation preferences, conversion points, and where the founders' share collapses.
mohitagw15856/pm-claude-skills
Apply prioritisation frameworks (RICE, MoSCoW, Kano, ICE, Opportunity Scoring) to rank features and backlog items.
mohitagw15856/pm-claude-skills
Compute a financial-independence (FIRE) target and years-to-reach with every assumption labeled as an assumption — plus a sensitivity table instead of a single false-precision answer.
mohitagw15856/pm-claude-skills
Derive a freelance day/hourly rate backwards from target income, honest billable utilization, overhead, and the self-employment tax premium — the arithmetic that proves a rate is not salary÷2000.
Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact. Change Order Writer is an agent skill from mohitagw15856/pm-claude-skills. Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact.
Change Order Writer fits situations like: asked to write a change order; price extra work; respond to a directive for changed work; paper a field change.
Run `npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a claude-code`. Or copy the skill folder (skills/change-order-writer in mohitagw15856/pm-claude-skills) into .claude/skills/change-order-writer in your project. Claude Code loads it when a task matches its description.
Run `npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a codex`. Or copy the skill folder (skills/change-order-writer in mohitagw15856/pm-claude-skills) into .agents/skills/change-order-writer in your project. Codex loads it when a task matches its description.
Cursor, Gemini CLI, GitHub Copilot and OpenCode also load SKILL.md folders. With the skills CLI, run `npx skills add mohitagw15856/pm-claude-skills --skill change-order-writer -a cursor` (or -a gemini-cli, github-copilot or opencode for the others). To copy it by hand, put the folder in .cursor/skills/change-order-writer, .gemini/skills/change-order-writer, .github/skills/change-order-writer and .opencode/skills/change-order-writer in your project.
SKILL.md names no scripts, command-line tools or credentials: Change Order Writer is instructions for the agent only.
SKILL.md contains no URLs. Any network use would come from the scripts or tools the agent runs. This is read from the text; nothing was executed.
Our automated static check of SKILL.md found no risky patterns, such as piping downloads into a shell, reading credential files or hidden Unicode. It is not a guarantee. Review the folder before installing.
Change Order Writer is published under the MIT licence (the repository's licence). It allows redistribution, so the full SKILL.md is shown on this page.
About 1.5k tokens (SKILL.md is roughly 5.9k characters). Agents keep only the skill's name and description in context until a task matches; then they load SKILL.md in full.
Skills that share tags, products or a category with Change Order Writer: Higher Order Article Writer (digoal/blog, 8.6k stars), CSS Order (thedaviddias/Front-End-Checklist, 74k stars), Focus Order (thedaviddias/Front-End-Checklist, 74k stars) and Heading Order (thedaviddias/Front-End-Checklist, 74k stars). The comparison table on this page puts their stars, adoption, token cost, safety result and licence side by side.
mohitagw15856 (a GitHub user) maintains it in mohitagw15856/pm-claude-skills, which has 1,434 GitHub stars. The repository holds 1,348 skills in this directory. The repository was last updated on October 9, 2026.
Source: mohitagw15856/pm-claude-skills on GitHub. Facts on this page come from the repository at the commit we read; the author's words are quoted as theirs.