Agent skill

Construction Progress Report

by LeoYeAI in LeoYeAI/openclaw-master-skills

Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document.

MITAuto-check passedProduct & Project Management

Install Construction Progress Report

skills CLI
$ npx skills add LeoYeAI/openclaw-master-skills --skill construction-progress-report -a claude-code

Project install by default; add -g for ~/.claude/skills/.

GitHub CLI
$ gh skill install LeoYeAI/openclaw-master-skills construction-progress-report --agent claude-code

Project scope by default; add --scope user for a personal install. Needs GitHub CLI 2.90.0 or later (public preview).

Manual copy
$ git clone --depth 1 https://github.com/LeoYeAI/openclaw-master-skills.git skills-src && mkdir -p .claude/skills && cp -r skills-src/skills/construction-progress-report .claude/skills/construction-progress-report && rm -rf skills-src

Use ~/.claude/skills/ instead of .claude/skills for a personal install. The folder must contain SKILL.md.

Claude Code skills documentation · loads skills from .claude/skills/

Facts

Skill name
construction-progress-report
GitHub stars
2.2k
Token cost
~4.1k tokens
SKILL.md length
1,693 words
Files
2
Skills in repo
1,215
Repo updated
First seen
Licence
MIT

At a glance

Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document.

  • Works in 5 steps: Establish Report Context → Conversational Interview — Section by… → Proactive Risk Detection → …
  • Tasks that involve Project management
  • SKILL.md covers Purpose, When to Activate, Instructions and Terminology, plus 3 more sections
  • Instructions only: no scripts, shell commands, URLs or credentials in SKILL.md

What it does

Construction Progress Report is an agent skill from LeoYeAI/openclaw-master-skills. Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document.

Its SKILL.md is about 4.1k tokens, which your agent loads only when the skill is triggered. The skill folder holds 1 other file (for example `_meta.json`).

It sits in Product & Project Management, covering Project management. The repository describes itself as: 🧠 Curated collection of 1209+ best OpenClaw skills — weekly updated by MyClaw.ai. The licence is MIT.

When your agent uses it

  • Tasks that involve Project management

Example prompts

  • “/construction-progress-report”

Workflow steps

5 steps, taken from the step headings in SKILL.md.

  1. Establish Report Context
  2. Conversational Interview — Section by Section
  3. Proactive Risk Detection
  4. Calculate Progress Metrics
  5. Generate the Report

What it can do on your machine

Read from SKILL.md and the folder at commit e5199b5. It shows what the files ask for, not the result of running them.

  • Tool permissions

    Pre-approves nothing: there is no allowed-tools line, so your agent's usual permission prompts apply.

    From allowed-tools in the SKILL.md frontmatter.

  • Runs code

    No scripts in the folder and no shell commands in SKILL.md.

    From the folder's file list and the shell code blocks in SKILL.md.

  • Network

    No URLs in SKILL.md.

    From URLs in SKILL.md, links to its own repository left out.

  • Credentials

    Names no API keys, tokens, secrets or passwords.

    From names ending in _API_KEY, _TOKEN, _SECRET, _KEY or _PASSWORD in SKILL.md.

Context cost

Construction Progress Report loads about 4.1k tokens when it runs. Until then it costs about 47 tokens; SKILL.md has 1,693 words of instructions outside code blocks.

Always · name and description, kept in context so the agent knows when to use it
~47
When it runs · the whole SKILL.md, loaded when a task matches
~4.1k

Estimates: characters ÷ 4, the usual rule of thumb; real counts depend on the model's tokenizer. Scripts and assets cost tokens only if the agent reads them.

Safety

Auto-check passed

The automated check found no risky patterns in SKILL.md.

Automated static check — not a guarantee. Review scripts before installing. It scans the text of SKILL.md for risky patterns (piping downloads into a shell, reading credential files, hidden Unicode, destructive commands); files beside SKILL.md are not scanned.

SKILL.md

The full file from LeoYeAI/openclaw-master-skills at commit e5199b5, republished under its MIT licence (© LeoYeAI). 1,693 words, ~4,149 tokens.

Download SKILL.mdSave it as .claude/skills/construction-progress-report/SKILL.md (or your agent's skills folder). This skill also uses 1 other file; get the full folder from GitHub.
name
construction-progress-report
description
Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document.
version
1.0.0
tags
construction, reporting, project-management, progress, weekly-report, monthly-report

Construction Progress Report Generator

Purpose

This skill helps project managers create polished weekly or monthly progress reports from conversational input. Instead of staring at a blank template, the PM talks to the agent — describing progress, issues, and plans in their own words — and the agent produces a professional, structured report suitable for distribution to clients, senior management, and stakeholders.

When to Activate

Activate this skill when:

  • The user mentions "progress report", "weekly report", "monthly report", or "project status report"
  • The user says "I need to write up the project report" or "help me with the progress update"
  • The user asks to summarise project status for a client or management meeting
  • The user wants to produce a report covering progress vs. programme, milestones, risks, and lookahead

Do NOT activate for daily site reports — use the construction-daily-report skill instead.

Instructions

You are a project reporting assistant for construction projects. Your job is to interview a project manager conversationally — asking about each section of the progress report, accepting rough and informal answers, and producing a polished, professional report that reads as if a senior PM wrote it. Follow these steps exactly:

Step 1: Establish Report Context

Before starting the interview, ALWAYS ask for:

  • Project name
  • Report period (e.g., "Week ending 22/03/2026" or "Month of February 2026")
  • Report type: Weekly or Monthly
  • Prepared by (name and role)
  • Distribution list (who will receive this report?)

Then say: "Great. I'll ask you about each section one at a time. Just answer naturally — I'll handle the formatting and polish. Let's go."

Step 2: Conversational Interview — Section by Section

Walk the PM through each section below. Ask ONE section at a time. Accept informal, rough answers. Do not overwhelm with multiple questions simultaneously.


Section 1: EXECUTIVE SUMMARY Ask: "Give me the high-level picture in 2-3 sentences. If the MD read only one paragraph of this report, what should they know?"

Agent instructions:

  • Capture the overall project health in 2-4 sentences
  • Include: overall progress percentage, on/behind/ahead of schedule, key achievement of the period, most significant concern
  • Write in confident, concise executive language

Section 2: OVERALL PROGRESS VS. PROGRAMME Ask: "How are we tracking against the programme? Are we on schedule, behind, or ahead? By how much?"

Agent instructions:

  • State planned vs. actual progress as a percentage if provided
  • If the user provides quantities (e.g., "60 of 120 piles done"), calculate the percentage: "50% complete (60/120 piles)"
  • Flag if behind schedule and by how much (days/weeks)
  • Use Earned Value language if the user provides cost/schedule data (SPI, CPI), but do not force this on users who speak in simpler terms
  • If the user provides multiple activities, create a progress table:
ActivityPlanned %Actual %Status
Piling75%50%🔴 Behind
Substructure30%35%🟢 Ahead

Section 3: KEY MILESTONES ACHIEVED THIS PERIOD Ask: "What were the main things you got done this [week/month]? Any milestones hit?"

Agent instructions:

  • List each milestone/achievement as a clear bullet point
  • Include dates where provided
  • Highlight contractual milestones distinctly from internal ones

Section 4: UPCOMING MILESTONES Ask: "What's coming up in the next [week/month]? Any key dates or milestones the team is working towards?"

Agent instructions:

  • List upcoming milestones with target dates
  • Flag any milestones at risk of slipping
  • Note dependencies or prerequisites

Section 5: CRITICAL PATH ITEMS Ask: "What activities are on the critical path right now? What's the thing that, if it slips, delays everything?"

Agent instructions:

  • Identify and describe critical path activities
  • Note any float remaining
  • Flag blockers or constraints affecting the critical path
  • If the user is unfamiliar with "critical path" terminology, rephrase: "What's the most time-sensitive activity right now — the one that holds up everything else if it's delayed?"

Section 6: RISKS AND ISSUES Ask: "What are the current risks or problems on the project? Anything keeping you up at night?"

Agent instructions:

  • Separate RISKS (things that might happen) from ISSUES (things that have happened)
  • For each risk/issue, capture: description, impact (schedule/cost/quality/safety), likelihood (if risk), mitigation/resolution, owner
  • Present as a risk/issue register table
  • IMPORTANT: Listen carefully to what the PM says throughout the entire interview. If they mention something that sounds like a risk or issue but don't categorise it as such (e.g., "the steel supplier keeps pushing back delivery dates"), capture it here and flag it: "I noticed you mentioned the steel delivery delays — I've added that to the risk register. Let me know if you want to remove it."

Section 7: CHANGE ORDERS / VARIATIONS Ask: "Any variations or change orders this period? New ones, or updates on existing ones?"

Agent instructions:

  • Track each variation with: VO number, description, status (submitted/under review/approved/rejected), cost impact, schedule impact
  • Distinguish between client-initiated and contractor-initiated variations
  • Note cumulative variation impact if the user provides it

Section 8: RESOURCE SUMMARY Ask: "How are we looking on resources — workforce numbers, key equipment, any shortages?"

Agent instructions:

  • Summarise peak/average workforce for the period
  • Note any key equipment mobilised or demobilised
  • Flag resource constraints or shortages
  • Note subcontractor performance issues if mentioned

Section 9: COMMERCIAL SUMMARY (Monthly reports only) Ask (if monthly): "How's the commercial side — where are we on the latest IPC, any outstanding payments, and what's the cost position?"

Agent instructions:

  • Only include this section in monthly reports
  • Cover: IPC submitted/certified, payments received, outstanding amounts, cost vs. budget position
  • Note any contractual claims or commercial disputes

Section 10: LOOKAHEAD Ask: "What's the plan for the next [2 weeks / month]? What should everyone expect?"

Agent instructions:

  • List planned activities for the upcoming period
  • Note any planned shutdowns, mobilisations, or key events
  • Highlight what resources or approvals are needed from the client or management

Section 11: PHOTOGRAPHS Ask: "Do you have any site photos to reference? Or should I note the key areas where photos should be taken?"

Agent instructions:

  • If the user sends photos, describe and classify them
  • If no photos, list suggested photo subjects based on the work described (e.g., "Recommended photos: Block A First Floor slab pour, scaffolding at Block C, stockpile area")

Show full SKILL.md (707 more words)Show less
Step 3: Proactive Risk Detection

Throughout the interview, you MUST listen for statements that indicate risks or issues, even when the PM doesn't explicitly flag them. Examples:

PM says...Agent detects...
"The steel is taking longer than expected"Supply chain delay risk
"We're waiting on the architect to update the drawings"Design information delay
"The subcontractor didn't show up yesterday"Subcontractor performance issue
"Client hasn't approved the variation yet"Approval bottleneck
"It's been raining all week"Weather impact on programme
"We might need more guys for the next phase"Resource constraint risk

When you detect something, note it to the user: "That sounds like it could be a risk to schedule — I'll add it to the risk register. Agreed?"

Step 4: Calculate Progress Metrics

If the user provides quantities, ALWAYS calculate progress percentages:

  • "60 of 120 piles" → 50% complete
  • "3,200m² of 5,000m² tiled" → 64% complete
  • "Level 4 of 8 levels complete" → 50% of structural frame

Present these calculations clearly in the report. Do not leave raw quantities without a percentage context.

Step 5: Generate the Report

Use professional but accessible language. The report will be read by clients, senior management, and project stakeholders. Avoid jargon that a non-construction reader would not understand, but keep technical precision where needed.

After generating, ALWAYS ask: "Here's the report. Shall I adjust anything before we finalise?"

Terminology

TermDefinition
ProgrammeConstruction schedule (Gantt chart showing activities and milestones)
Critical PathThe longest sequence of dependent activities — determines the minimum project duration
FloatThe amount of time an activity can slip without affecting the project end date
SPISchedule Performance Index (Earned Value) — 1.0 = on schedule, <1.0 = behind
CPICost Performance Index (Earned Value) — 1.0 = on budget, <1.0 = over budget
EVMEarned Value Management — a method for measuring project performance
BACBudget at Completion — the total approved project budget
IPCInterim Payment Certificate — monthly progress payment claim
VOVariation Order — a formal change to the contract
RFIRequest for Information
LookaheadA short-term plan (typically 2-4 weeks) showing upcoming activities
SubstructureBuilding work below ground level (foundations, basement)
SuperstructureBuilding work above ground level (columns, beams, slabs, walls)
M&EMechanical and Electrical works (plumbing, HVAC, electrical installations)

Output Format

═══════════════════════════════════════════════════════
       [WEEKLY/MONTHLY] PROGRESS REPORT
═══════════════════════════════════════════════════════

Project:        [Project Name]
Report Period:  [Week ending DD/MM/YYYY or Month YYYY]
Report No:      [Sequential Number]
Prepared By:    [Name, Role]
Date Issued:    [DD/MM/YYYY]
Distribution:   [Names/Roles]

───────────────────────────────────────────────────────
1. EXECUTIVE SUMMARY
───────────────────────────────────────────────────────
[2-4 sentences: overall health, progress %, key achievement, key concern]

───────────────────────────────────────────────────────
2. PROGRESS VS. PROGRAMME
───────────────────────────────────────────────────────
Overall Planned Progress:  [X%]
Overall Actual Progress:   [X%]
Variance:                  [+/-X%] — [Ahead/Behind/On Schedule]

| Activity             | Planned % | Actual % | Variance | Status |
|---------------------|-----------|----------|----------|--------|
| [Activity 1]        | [X%]      | [X%]     | [+/-X%]  | [🟢🟡🔴] |
| ...                 | ...       | ...      | ...      | ...    |

[Narrative explanation of variance]

───────────────────────────────────────────────────────
3. KEY MILESTONES ACHIEVED
───────────────────────────────────────────────────────
- [Milestone 1] — [Date achieved]
- [Milestone 2] — [Date achieved]

───────────────────────────────────────────────────────
4. UPCOMING MILESTONES
───────────────────────────────────────────────────────
| Milestone                | Target Date | Status        |
|-------------------------|-------------|---------------|
| [Milestone 1]           | [Date]      | [On Track/At Risk] |
| ...                     | ...         | ...           |

───────────────────────────────────────────────────────
5. CRITICAL PATH ITEMS
───────────────────────────────────────────────────────
[Description of critical path activities, constraints, and float]

───────────────────────────────────────────────────────
6. RISKS AND ISSUES
───────────────────────────────────────────────────────
| # | Type  | Description          | Impact        | Likelihood | Mitigation           | Owner  |
|---|-------|---------------------|---------------|------------|---------------------|--------|
| 1 | Risk  | [Description]       | [S/C/Q/Safety]| [H/M/L]    | [Mitigation action] | [Name] |
| 2 | Issue | [Description]       | [Impact desc] | —          | [Resolution action] | [Name] |

───────────────────────────────────────────────────────
7. CHANGE ORDERS / VARIATIONS
───────────────────────────────────────────────────────
| VO No. | Description       | Status       | Cost Impact    | Schedule Impact |
|--------|------------------|-------------|----------------|----------------|
| [No.]  | [Description]    | [Status]    | [Amount]       | [+/- days]     |

Cumulative Variation Impact: [Total amount]

───────────────────────────────────────────────────────
8. RESOURCE SUMMARY
───────────────────────────────────────────────────────
Average Workforce This Period: [Number]
Peak Workforce:                [Number]
Key Equipment:                 [List]
Resource Issues:               [Description or "None"]

───────────────────────────────────────────────────────
[9. COMMERCIAL SUMMARY — Monthly reports only]
───────────────────────────────────────────────────────
IPC Status:          [IPC No. X submitted/certified — Amount]
Payments Received:   [Amount — Date]
Outstanding:         [Amount]
Cost vs. Budget:     [On budget / X% over / X% under]

───────────────────────────────────────────────────────
10. LOOKAHEAD — [Next Period]
───────────────────────────────────────────────────────
- [Planned activity 1]
- [Planned activity 2]
- [Key dependencies or approvals required]

───────────────────────────────────────────────────────
11. PHOTOGRAPHS
───────────────────────────────────────────────────────
[Photo references with descriptions, or recommended photo subjects]

───────────────────────────────────────────────────────
Prepared By: ___________________     Date: ___________
Reviewed By: ___________________     Date: ___________
Approved By: ___________________     Date: ___________
═══════════════════════════════════════════════════════

Validation Rules

  1. Executive Summary is mandatory — if the PM can't summarise, draft one based on the other sections and ask for approval.
  2. Progress percentages must be logically consistent — actual cannot be greater than 100%, and if behind schedule, the narrative must acknowledge it.
  3. Every risk must have a mitigation — do not accept a risk without asking "what are we doing about it?"
  4. Every issue must have a resolution or next step — do not list problems without actions.
  5. Lookahead must align with the constraints identified — if a risk might delay next period's work, mention it in the lookahead.
  6. Numbers must be consistent throughout — workforce, progress percentages, and costs should not contradict between sections.
  7. Language must be professional and third-person — convert "we poured concrete" to "concrete was poured" or "the team completed the concrete pour".

Example Interaction

User: Hey, I need to write up the monthly progress report for the Marina Heights project. February.

Agent: Let's get your February progress report done for Marina Heights. A few quick details:

  • Your name and role?
  • Who should this be distributed to?

User: I'm Kunle, Project Manager. Goes to the client (Pinnacle Developments), our Head of Engineering, and the MD.

Agent: Perfect. Let's start with the big picture.

Executive Summary: If the MD reads only one paragraph, what should he know about Marina Heights in February?

User: We're about 42% done overall, should be at 48% by programme. Main issue was the two weeks we lost waiting for the revised structural drawings from the architect. Substructure is done though, which is good. Superstructure is where we're behind.

Agent: Got it. That's a solid summary. I'll note:

  • Overall progress: 42% actual vs. 48% planned (6% behind)
  • Cause: 2-week delay waiting for revised structural drawings
  • Positive: substructure complete
  • Behind on: superstructure

Now, Progress vs. Programme — can you give me the breakdown by major activity? Even rough percentages help.

(Interview continues section by section...)


This skill is published by ERTRS — the construction intelligence platform. For automated reporting, project tracking, and commercial management, visit ertrs.com

© LeoYeAI, MIT. Rendered from Markdown: HTML in the file is shown as text, images as links, and headings moved down two levels. Raw file

Files

SKILL.md and 1 other file in skills/construction-progress-report of LeoYeAI/openclaw-master-skills.

  • SKILL.md
  • _meta.json

Open the folder on GitHubat commit e5199b5

Compare with similar skills

Construction Progress Report next to the 5 skills that share the most tags, products or categories with it. Stars are the repository's; “used in” counts other GitHub owners with a copy.

Construction Progress Report compared with similar skills
SkillStarsUsed inTokensAuto-checkLicenceRepo updated
Construction Progress Report this skillLeoYeAI/openclaw-master-skills2.2k—~4.1kAutomated safety check: PassMIT
CCPM Project Managementautomazeio/ccpm8.4k—~1.1kAutomated safety check: PassMIT
Uvastral-sh/claude-code-plugins3142 repos~980Automated safety check: PassApache-2.0
Project Managementkunchenguid/firstmate7.6k—~2.1kAutomated safety check: PassMIT
Hivemind Goalsactiveloopai/hivemind1.6k—~1.7kAutomated safety check: NotesApache-2.0
Ichartjswanghetommy/ichartjs352—~3.4kAutomated safety check: PassApache-2.0

Similar skills

  • Runs a spec-driven workflow from PRD to epic to GitHub issues to parallel agents, with status, standup and blocked-work reports from bundled scripts.

    8.4k GitHub stars~1.1k tokensUpdated 6 mo ago
    Product & Project ManagementAuto-check passed
  • Uv

    astral-sh/claude-code-plugins

    Official

    Guide for using uv, the Python package and project manager. An agent skill from astral-sh/claude-code-plugins.

    314 GitHub starsUsed in 2 repos~980 tokens
    Product & Project ManagementAuto-check passed
  • Project Management

    kunchenguid/firstmate

    Agent-only procedure for Firstmate project management. An agent skill from kunchenguid/firstmate.

    7.6k GitHub stars~2.1k tokensUpdated today
    Product & Project ManagementAuto-check passed
  • Hivemind Goals

    activeloopai/hivemind

    Create, track and update team goals via the Deeplake virtual filesystem at memory/goal/.

    1.6k GitHub stars~1.7k tokensUpdated 9 days ago
    Product & Project ManagementAuto-check: notes
  • Ichartjs

    wanghetommy/ichartjs

    Plan, validate, render, explain, and safely edit iChart.js visualizations from tabular, project, or diagram data.

    352 GitHub stars~3.4k tokensUpdated yesterday
    Product & Project ManagementAuto-check passed
  • Hivemind Goals

    activeloopai/hivemind

    Create, track and update team goals in Hivemind via the hivemind CLI.

    1.6k GitHub stars~814 tokensUpdated 9 days ago
    Product & Project ManagementAuto-check passed

More from LeoYeAI/openclaw-master-skills

All 1,215 skills in this repo
  • DevOps Pipeline Management

    LeoYeAI/openclaw-master-skills

    Manages pipelines on a DevOps quality and efficiency platform through its OpenAPI: list workspaces and templates, create, update, run and cancel pipelines, and read run records.

    2.2k GitHub stars~4.2k tokensUpdated 2 mo ago
    Auto-check: notes
  • Feishu Document Collaboration

    LeoYeAI/openclaw-master-skills

    Patches OpenClaw's Feishu extension so an edited document triggers an isolated agent session that reads the doc and replies inline, turning it into a live chat space.

    2.2k GitHub stars~2k tokensUpdated 2 mo ago
    Auto-check passed
  • Files Memory System

    LeoYeAI/openclaw-master-skills

    Multi-context memory management system for OpenClaw agents with group-isolated storage, global shared memory, workspace organization, and group-specific skills isolation.

    2.2k GitHub stars~3.8k tokensUpdated 2 mo ago
    Auto-check passed
  • GEO-Claw AI Visibility Agent

    LeoYeAI/openclaw-master-skills

    Runs a brand's AI-search visibility work end to end: diagnosing how AI platforms represent it, repositioning it, producing AI-optimized content and monitoring ongoing mentions.

    2.2k GitHub stars~4.7k tokensUpdated 2 mo ago
    Auto-check passed
  • Google Workspace CLI

    LeoYeAI/openclaw-master-skills

    Installs and authenticates the gws CLI, then automates Gmail, Drive, Sheets, Calendar, Docs, Chat and Tasks with ready-made recipes, persona bundles and security audits.

    2.2k GitHub stars~2.6k tokensUpdated 2 mo ago
    Auto-check: notes
  • HealthFit Health Advisors

    LeoYeAI/openclaw-master-skills

    Runs four advisor roles, a fitness coach, nutritionist, data analyst and TCM practitioner, to build a health profile and track workouts, diet and wellness over time.

    2.2k GitHub stars~4.4k tokensUpdated 2 mo ago
    Auto-check passed

Questions about Construction Progress Report

What does Construction Progress Report do?

Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document. Construction Progress Report is an agent skill from LeoYeAI/openclaw-master-skills. Help a project manager create a structured weekly or monthly construction progress report from conversational input, producing a polished professional document.

When should I use Construction Progress Report?

Construction Progress Report fits situations like: tasks that involve Project management.

How do I install Construction Progress Report in Claude Code?

Run `npx skills add LeoYeAI/openclaw-master-skills --skill construction-progress-report -a claude-code`. Or copy the skill folder (skills/construction-progress-report in LeoYeAI/openclaw-master-skills) into .claude/skills/construction-progress-report in your project. Claude Code loads it when a task matches its description.

How do I install Construction Progress Report in Codex?

Run `npx skills add LeoYeAI/openclaw-master-skills --skill construction-progress-report -a codex`. Or copy the skill folder (skills/construction-progress-report in LeoYeAI/openclaw-master-skills) into .agents/skills/construction-progress-report in your project. Codex loads it when a task matches its description.

Can I use Construction Progress Report in Cursor, Gemini CLI or GitHub Copilot?

Cursor, Gemini CLI, GitHub Copilot and OpenCode also load SKILL.md folders. With the skills CLI, run `npx skills add LeoYeAI/openclaw-master-skills --skill construction-progress-report -a cursor` (or -a gemini-cli, github-copilot or opencode for the others). To copy it by hand, put the folder in .cursor/skills/construction-progress-report, .gemini/skills/construction-progress-report, .github/skills/construction-progress-report and .opencode/skills/construction-progress-report in your project.

What does Construction Progress Report need to run?

SKILL.md names no scripts, command-line tools or credentials: Construction Progress Report is instructions for the agent only.

Does Construction Progress Report access the network?

SKILL.md contains no URLs. Any network use would come from the scripts or tools the agent runs. This is read from the text; nothing was executed.

Is Construction Progress Report safe to install?

Our automated static check of SKILL.md found no risky patterns, such as piping downloads into a shell, reading credential files or hidden Unicode. It is not a guarantee. Review the folder before installing.

What licence does Construction Progress Report use?

Construction Progress Report is published under the MIT licence (the repository's licence). It allows redistribution, so the full SKILL.md is shown on this page.

How many tokens does Construction Progress Report use?

About 4.1k tokens (SKILL.md is roughly 17k characters). Agents keep only the skill's name and description in context until a task matches; then they load SKILL.md in full.

What are the alternatives to Construction Progress Report?

Skills that share tags, products or a category with Construction Progress Report: CCPM Project Management (automazeio/ccpm, 8.4k stars), Uv (astral-sh/claude-code-plugins, 314 stars), Project Management (kunchenguid/firstmate, 7.6k stars) and Hivemind Goals (activeloopai/hivemind, 1.6k stars). The comparison table on this page puts their stars, adoption, token cost, safety result and licence side by side.

Who maintains Construction Progress Report?

LeoYeAI (a GitHub user) maintains it in LeoYeAI/openclaw-master-skills, which has 2,158 GitHub stars. The repository holds 1,215 skills in this directory. The repository was last updated on July 20, 2026.

Source: LeoYeAI/openclaw-master-skills on GitHub. Facts on this page come from the repository at the commit we read; the author's words are quoted as theirs.