Agent skill

Afrexai Construction Estimator

by LeoYeAI in LeoYeAI/openclaw-master-skills

Complete construction estimating and cost management system.

MITAuto-check passedSales & Support

Install Afrexai Construction Estimator

skills CLI
$ npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator -a claude-code

Project install by default; add -g for ~/.claude/skills/.

GitHub CLI
$ gh skill install LeoYeAI/openclaw-master-skills afrexai-construction-estimator --agent claude-code

Project scope by default; add --scope user for a personal install. Needs GitHub CLI 2.90.0 or later (public preview).

Manual copy
$ git clone --depth 1 https://github.com/LeoYeAI/openclaw-master-skills.git skills-src && mkdir -p .claude/skills && cp -r skills-src/skills/afrexai-construction-estimator .claude/skills/afrexai-construction-estimator && rm -rf skills-src

Use ~/.claude/skills/ instead of .claude/skills for a personal install. The folder must contain SKILL.md.

Claude Code skills documentation · loads skills from .claude/skills/

Facts

Skill name
afrexai-construction-estimator
GitHub stars
2.2k
Token cost
~6.1k tokens
SKILL.md length
2,077 words
Files
3
Skills in repo
1,235
Repo updated
First seen
Licence
MIT

At a glance

Complete construction estimating and cost management system.

  • Works in 12 steps: Project Classification & Estimate Type → Quantity Takeoff (QTO) → Pricing & Cost Assembly → …
  • Preparing project estimates
  • SKILL.md covers Phase 1: Project…, Phase 2: Quantity Takeoff (QTO), Phase 3: Pricing & Cost Assembly and Phase 4: Indirect Costs &…, plus 3 more sections
  • Instructions only: no scripts, shell commands, URLs or credentials in SKILL.md

What it does

Afrexai Construction Estimator is an agent skill from LeoYeAI/openclaw-master-skills. Complete construction estimating and cost management system. Use when preparing project estimates, bid proposals, cost breakdowns, value engineering, change order management, or construction budget tracking. Covers residential, commercial, and infrastructure projects. Trigger on 'estimate', 'construction cost', 'bid', 'takeoff', 'cost breakdown', 'change order', 'value engineering', 'construction budget', 'unit pricing', 'RSMeans'.

Its SKILL.md is about 6.1k tokens, which your agent loads only when the skill is triggered. The skill folder holds 2 other files (for example `README.md` and `_meta.json`).

It sits in Sales & Support, covering Cloud cost optimization, Proposals and quotes and E-commerce operations. The repository describes itself as: 🧠 Curated collection of 1209+ best OpenClaw skills — weekly updated by MyClaw.ai. The licence is MIT.

When your agent uses it

  • Preparing project estimates
  • Cost breakdowns
  • Value engineering
  • Change order management

Example prompts

  • “estimate”
  • “construction cost”
  • “takeoff”
  • “/afrexai-construction-estimator”

Workflow steps

12 steps, taken from the step headings in SKILL.md.

  1. Project Classification & Estimate Type
  2. Quantity Takeoff (QTO)
  3. Pricing & Cost Assembly
  4. Indirect Costs & Markups
  5. Bid Preparation & Strategy
  6. Value Engineering (VE)
  7. Change Order Management
  8. Cost Control During Construction
  9. Specialty Estimate Types
  10. Escalation & Location Adjustments
  11. Estimate Quality Review
  12. Common Mistakes & Edge Cases

What it can do on your machine

Read from SKILL.md and the folder at commit e5199b5. It shows what the files ask for, not the result of running them.

  • Tool permissions

    Pre-approves nothing: there is no allowed-tools line, so your agent's usual permission prompts apply.

    From allowed-tools in the SKILL.md frontmatter.

  • Runs code

    No scripts in the folder and no shell commands in SKILL.md (its code samples are yaml).

    From the folder's file list and the shell code blocks in SKILL.md.

  • Network

    No URLs in SKILL.md.

    From URLs in SKILL.md, links to its own repository left out.

  • Credentials

    Names no API keys, tokens, secrets or passwords.

    From names ending in _API_KEY, _TOKEN, _SECRET, _KEY or _PASSWORD in SKILL.md.

Context cost

Afrexai Construction Estimator loads about 6.1k tokens when it runs. Until then it costs about 117 tokens; SKILL.md has 2,077 words of instructions outside code blocks.

Always · name and description, kept in context so the agent knows when to use it
~117
When it runs · the whole SKILL.md, loaded when a task matches
~6.1k

Estimates: characters ÷ 4, the usual rule of thumb; real counts depend on the model's tokenizer. Scripts and assets cost tokens only if the agent reads them.

Safety

Auto-check passed

The automated check found no risky patterns in SKILL.md.

Automated static check — not a guarantee. Review scripts before installing. It scans the text of SKILL.md for risky patterns (piping downloads into a shell, reading credential files, hidden Unicode, destructive commands); files beside SKILL.md are not scanned.

SKILL.md

The full file from LeoYeAI/openclaw-master-skills at commit e5199b5, republished under its MIT licence (© LeoYeAI). 2,077 words, ~6,083 tokens.

Download SKILL.mdSave it as .claude/skills/afrexai-construction-estimator/SKILL.md (or your agent's skills folder). This skill also uses 2 other files; get the full folder from GitHub.
name
afrexai-construction-estimator
description
Complete construction estimating and cost management system. Use when preparing project estimates, bid proposals, cost breakdowns, value engineering, change order management, or construction budget tracking. Covers residential, commercial, and infrastructure projects. Trigger on 'estimate', 'construction cost', 'bid', 'takeoff', 'cost breakdown', 'change order', 'value engineering', 'construction budget', 'unit pricing', 'RSMeans'.

Construction Estimator Pro

Complete construction estimating methodology — from quantity takeoff to bid submission. Zero dependencies.


Phase 1: Project Classification & Estimate Type

Estimate Type Decision Matrix
Project StageEstimate TypeAccuracyBasisUse Case
ConceptOrder of Magnitude-30% to +50%SF/unit costsGo/no-go decisions
SchematicConceptual/Budget-15% to +30%Assembly costsBudget approval
Design DevDetailed-10% to +15%Quantity takeoffGMP/bid preparation
Construction DocsDefinitive/Bid-5% to +10%Full QTO + subsLump sum bid
ConstructionControlActual costsCommitted + forecastCost management
Project Brief YAML
yaml
project:
  name: ""
  number: ""
  type: residential | commercial | industrial | infrastructure | renovation
  delivery: design-bid-build | design-build | CM-at-risk | IPD
  location:
    city: ""
    state: ""
    zip: ""
    location_factor: 1.00  # RSMeans city cost index / national average
  owner: ""
  architect: ""
  
scope:
  gross_sf: 0
  stories: 0
  site_acres: 0
  description: ""
  
schedule:
  bid_date: ""
  construction_start: ""
  substantial_completion: ""
  duration_months: 0
  
estimate:
  type: order-of-magnitude | conceptual | detailed | definitive
  base_date: ""  # Date costs are based on
  escalation_rate: 0.04  # Annual construction cost escalation
  
assumptions:
  - ""
exclusions:
  - ""
allowances:
  - item: ""
    amount: 0
Project Type Quick Reference
TypeKey ConsiderationsTypical $/SF Range (2024-2026)
Single Family ResidentialFoundation type, finishes grade, energy code$150-$400/SF
Multi-FamilyUnit mix, parking ratio, amenities$200-$450/SF
Office (Class A)Curtain wall, MEP density, TI allowance$250-$550/SF
RetailShell vs TI, storefront, grease traps$150-$350/SF
Healthcare/HospitalLife safety, med gas, shielding$400-$900/SF
K-12 EducationPrevailing wage, hazmat, phasing$300-$600/SF
Warehouse/DistributionClear height, slab flatness, dock count$80-$180/SF
HotelStar rating drives finish, FF&E budget$200-$500/SF
Infrastructure (road/mile)Soil conditions, utilities, traffic control$2M-$10M/mile

Phase 2: Quantity Takeoff (QTO)

CSI MasterFormat Division Structure

Use CSI MasterFormat 2018 for ALL estimates. Every line item maps to a division.

DivisionNameTypical % of Total
01General Requirements8-12%
02Existing Conditions1-5%
03Concrete8-15%
04Masonry2-6%
05Metals (Structural Steel)8-15%
06Wood, Plastics, Composites3-8%
07Thermal & Moisture Protection4-8%
08Openings (Doors/Windows)3-7%
09Finishes8-15%
10Specialties1-3%
11Equipment1-5%
12Furnishings1-5%
13Special Construction0-3%
14Conveying Equipment (Elevators)1-4%
21Fire Suppression2-4%
22Plumbing4-8%
23HVAC8-15%
26Electrical8-15%
27Communications1-3%
28Electronic Safety & Security1-3%
31Earthwork3-8%
32Exterior Improvements2-6%
33Utilities2-5%
QTO Best Practices
  1. Measure twice, price once — QTO errors cascade through the entire estimate
  2. Use consistent units — SF for areas, LF for linear, CY for volume, EA for items
  3. Add waste factors by material:
    • Concrete: 5-8%
    • Masonry: 3-5%
    • Drywall: 10-12%
    • Roofing: 8-10%
    • Flooring (tile): 10-15%
    • Lumber: 8-10%
    • Rebar: 5-7%
    • Paint: 10-15%
  4. Document measurement methodology — so anyone can verify
  5. Cross-check totals — SF of drywall ≈ 2.5-3x floor area (both sides of walls + ceilings)
QTO Line Item Template
yaml
line_item:
  division: "03"
  spec_section: "03 30 00"
  description: "Cast-in-Place Concrete - Elevated Slabs"
  quantity: 450
  unit: CY
  unit_cost:
    labor: 85.00
    material: 165.00
    equipment: 25.00
    subcontractor: 0.00
  total_unit_cost: 275.00
  extended_cost: 123750.00
  waste_factor: 0.07
  adjusted_quantity: 481.5
  notes: "4500 PSI, #5 rebar @ 12\" OC EW, 6\" slab"
  source: "Sub quote - ABC Concrete (02/15/2026)"
  confidence: high | medium | low
Quantity Verification Cross-Checks
CheckFormulaFlag If
Concrete per SFTotal CY ÷ Building SF>0.15 CY/SF (unless heavy structure)
Steel per SFTotal tons ÷ Building SF>15 PSF (unless high-rise)
Drywall SFTotal drywall SF ÷ Floor SF<2.0 or >4.0 ratio
Electrical per SFElectrical $ ÷ Building SF>$35/SF (standard office)
Plumbing fixturesCount vs occupancyMissing fixtures for code compliance
Parking spacesPer local code requirementsBelow minimum ratio

Phase 3: Pricing & Cost Assembly

Unit Cost Development

Cost source hierarchy (most reliable first):

  1. Subcontractor quotes (3 minimum per trade) — best for bid estimates
  2. Historical project data — adjusted for location, time, scope
  3. RSMeans/Gordian data — industry standard reference
  4. Vendor quotes — for specific materials/equipment
  5. Published cost guides — Marshall & Swift, Craftsman
Labor Cost Build-Up
yaml
labor_rate_build_up:
  trade: "Carpenter"
  base_wage: 42.50
  fringe_benefits: 18.75   # Health, pension, vacation, training
  payroll_taxes: 8.90      # FICA, FUTA, SUTA, workers comp
  total_burden: 27.65
  burdened_rate: 70.15
  
  productivity_factors:
    weather: 1.00           # 1.0 = normal, 1.15 = winter
    overtime: 1.00          # 1.0 = straight time, 1.5 = OT
    height: 1.00            # 1.0 = ground, 1.10 = >30ft
    congestion: 1.00        # 1.0 = open, 1.15 = tight
    shift: 1.00             # 1.0 = day, 1.10 = swing, 1.15 = night
  adjusted_rate: 70.15
Subcontractor Quote Evaluation

Score each sub quote (use minimum 3 per trade):

FactorWeight1-5 Score
Price competitiveness30%
Scope completeness (covers all spec sections?)25%
Qualifications/exclusions (red flags?)20%
Past performance/reputation15%
Bond capacity/insurance10%
Weighted Total100%

Red flags in sub quotes:

  • "As needed" or "TBD" line items (scope gap)
  • Short validity period (<30 days)
  • Unusual exclusions (e.g., electrician excluding wire)
  • No reference to spec sections
  • Price significantly below others (they missed something)
Crew Rate Assembly
Crew Daily Cost = Σ(Workers × Daily Rate) + Equipment Daily Cost
Crew Daily Output = Units per 8-hour day (from labor standards)
Unit Cost = Crew Daily Cost ÷ Crew Daily Output

Example — Concrete Placement Crew:

  • 1 Foreman @ $75/hr × 8 = $600
  • 4 Laborers @ $55/hr × 8 = $1,760
  • 1 Vibrator operator @ $60/hr × 8 = $480
  • Concrete pump (daily rental) = $1,200
  • Crew Daily Cost = $4,040
  • Daily output: 50 CY
  • Unit Labor+Equipment Cost = $80.80/CY
  • Material (concrete delivered) = $165/CY
  • Total in-place cost = $245.80/CY

Phase 4: Indirect Costs & Markups

General Conditions (Division 01) Checklist
ItemDuration-Based?Typical Range
Project ManagerYes$12K-$18K/month
SuperintendentYes$10K-$16K/month
Project EngineerYes$8K-$12K/month
Field Office (trailer)Yes$1K-$3K/month
Temporary utilitiesYes$2K-$5K/month
Temporary toiletsYes$200-$500/month each
Dumpsters/waste removalYes$1K-$4K/month
Safety equipment/suppliesYes$500-$2K/month
Small tools & consumablesLump1-2% of labor
Final cleaningLump$0.15-$0.50/SF
Permits (building)LumpVaries by jurisdiction
Insurance (Builder's Risk)Lump0.5-1.5% of cost
Performance/Payment BondLump1-3% of contract
Testing & inspectionLump0.5-1.5% of cost
As-built documentationLump$5K-$25K
Commissioning supportLump$10K-$50K

Rule of thumb: General conditions = 8-15% of direct costs (lower for large projects, higher for small/complex).

Markup Stack
yaml
markup_calculation:
  direct_costs: 2500000
  
  general_conditions:
    percentage: 0.10
    amount: 250000
    
  subtotal_1: 2750000
  
  overhead:
    percentage: 0.05     # Home office overhead
    amount: 137500
    
  subtotal_2: 2887500
  
  profit:
    percentage: 0.05     # Varies by market/risk
    amount: 144375
    
  subtotal_3: 3031875
  
  contingency:
    design_contingency: 0.05    # For incomplete drawings
    construction_contingency: 0.03  # For unforeseen conditions
    amount: 242550
    
  bond:
    percentage: 0.015
    amount: 49118
    
  escalation:
    rate: 0.04           # Annual
    months_to_midpoint: 8
    amount: 88536
    
  total_estimate: 3412079
  cost_per_sf: 341.21    # For 10,000 SF building
Contingency Guide
Estimate TypeDesign ContingencyConstruction Contingency
Order of Magnitude15-25%10-15%
Conceptual10-15%5-10%
Detailed3-8%3-5%
Definitive/Bid0-3%2-3%

Contingency is NOT profit padding. Track and justify every contingency draw.


Phase 5: Bid Preparation & Strategy

Bid/No-Bid Decision Scorecard

Score 1-5 for each (minimum 30 to bid):

FactorWeightScore
Project type experience3x
Client relationship/history2x
Current workload capacity3x
Geographic fit2x
Profit potential3x
Competition level (fewer = better)2x
Risk profile (lower = better)3x
Schedule feasibility2x
Bonding capacity available2x
Weighted Total/110
Bid Day Checklist

48 hours before:

  • All sub quotes received (minimum 3 per trade)
  • All material quotes current (check expiration dates)
  • Addenda reviewed and incorporated (ALL of them)
  • Scope gaps identified and plugged
  • Math verified (independent check)

Day of bid:

  • Final sub quotes plugged in
  • Markup/profit decision finalized
  • Alternates priced if required
  • Unit prices calculated if required
  • Bid bond secured
  • Bid form completed correctly (every blank filled)
  • Acknowledge ALL addenda on bid form
  • Authorized signature
  • Delivered before deadline (allow 1+ hour buffer)
Competitive Bid Strategy

Market conditions affect markup:

  • Hot market (lots of work): Markup 8-12% (O&P combined)
  • Normal market: Markup 6-10%
  • Slow market: Markup 3-6%
  • Must-win/strategic: Markup 2-4% (minimum to cover overhead)

Bid spread analysis (track your results):

Bid Spread = (Your Bid - Low Bid) ÷ Low Bid × 100
  • Consistently >10% high → Your costs are inflated or productivity assumptions too conservative
  • Consistently <2% from low → You might be leaving money on the table
  • Target: Within 3-5% of winning bid

Phase 6: Value Engineering (VE)

VE Opportunity Matrix
SystemVE OpportunityTypical SavingsRisk Level
StructuralSteel vs concrete frame5-15% of structureMedium
FoundationsSpread vs mat vs piles10-30% of foundationHigh (geotech dependent)
EnvelopeCurtain wall vs storefront15-30% of facadeLow-Medium
RoofingTPO vs modified bitumen10-20% of roofingLow
MechanicalVAV vs VRF10-25% of HVACMedium
ElectricalLED fixtures, panel optimization5-15% of electricalLow
FinishesMaterial substitutions10-40% of finishesLow
SiteReduce import/export of soil10-30% of siteworkMedium
VE Proposal Template
yaml
ve_item:
  number: VE-001
  description: "Substitute VRF system for conventional VAV"
  division: "23"
  
  original:
    description: "VAV air handling system with ductwork"
    cost: 850000
    
  proposed:
    description: "Variable Refrigerant Flow (VRF) with DOAS"
    cost: 680000
    
  savings: 170000
  savings_pct: 20%
  
  impact:
    schedule: "Reduces mechanical rough-in by 2 weeks"
    quality: "Better zone control, lower operating cost"
    maintenance: "Higher per-unit cost but less ductwork"
    code_compliance: "Meets ASHRAE 90.1, verify local amendments"
    
  risk: medium
  recommendation: accept | reject | modify
  requires_redesign: yes | no
  redesign_cost: 15000
  net_savings: 155000
VE Decision Rules
  1. Never VE life safety — fire protection, structural integrity, egress
  2. Calculate lifecycle cost — cheap upfront ≠ cheap over 20 years
  3. Get architect/engineer sign-off before bidding VE alternates
  4. Document everything — VE that isn't documented becomes a scope gap
  5. Owner decides — present options with data, let them choose

Phase 7: Change Order Management

Change Order Pricing Rules

Contractor markup on changes (typical):

TierSelf-Performed WorkSubcontractor Work
Overhead10%5%
Profit10%5%
BondAdd actual %Add actual %

Time & Material (T&M) documentation requirements:

  • Daily time sheets signed by owner's rep
  • Material invoices with delivery tickets
  • Equipment logs with hours
  • Photos of work in progress
Change Order YAML Template
yaml
change_order:
  number: CO-001
  date: ""
  description: ""
  
  reason:
    type: owner-directed | unforeseen-condition | design-error | code-change | scope-clarification
    rfi_number: ""
    
  cost_breakdown:
    labor:
      hours: 0
      rate: 0
      total: 0
    material:
      items: []
      total: 0
    equipment:
      items: []
      total: 0
    subcontractor:
      items: []
      total: 0
    direct_cost: 0
    markup: 0.15
    total_cost: 0
    
  schedule_impact:
    days: 0
    critical_path: yes | no
    explanation: ""
    
  status: pending | approved | rejected | negotiating
Change Order Negotiation Tips
  1. Price it immediately — delay weakens your position
  2. Submit with backup — labor rates, material quotes, productivity analysis
  3. Separate time from money — negotiate schedule impact independently
  4. Track cumulative impact — 20 small changes = major schedule disruption (even if each is "0 days")
  5. Constructive acceleration — if owner delays approval but expects same completion, document it
  6. Unit price book — agree on unit prices at contract start for common change types

Phase 8: Cost Control During Construction

Earned Value Management (EVM)
Budget at Completion (BAC) = Total budget
Planned Value (PV) = Budgeted cost of work scheduled
Earned Value (EV) = Budgeted cost of work performed
Actual Cost (AC) = Actual cost of work performed

Schedule Performance Index (SPI) = EV / PV
  >1.0 = ahead of schedule
  <1.0 = behind schedule

Cost Performance Index (CPI) = EV / AC
  >1.0 = under budget
  <1.0 = over budget

Estimate at Completion (EAC) = BAC / CPI
Variance at Completion (VAC) = BAC - EAC
Show full SKILL.md (832 more words)Show less
Monthly Cost Report Template
yaml
cost_report:
  project: ""
  period: ""
  report_date: ""
  
  summary:
    original_contract: 0
    approved_changes: 0
    pending_changes: 0
    current_budget: 0
    committed_cost: 0      # Subcontracts + POs
    actual_cost_to_date: 0
    forecast_to_complete: 0
    estimate_at_completion: 0
    variance: 0
    contingency_remaining: 0
    
  schedule:
    percent_complete: 0
    spi: 0
    cpi: 0
    days_ahead_behind: 0
    
  cash_flow:
    billed_to_date: 0
    collected_to_date: 0
    retention_held: 0
    
  risk_items:
    - description: ""
      potential_cost: 0
      probability: high | medium | low
      mitigation: ""
Cost Control Red Flags
SignalWhat It MeansAction
CPI < 0.95 in first 25%Systemic cost overrunRoot cause analysis NOW
Contingency burn > schedule %Burning contingency too fastTighten change management
>5 pending COs unsignedCash flow risk, scope disputeEscalate to PM/owner
Sub invoices > committedSub performing extra workVerify scope, issue CO or stop work
Retainage release requests earlySub cash flow problemsMonitor closely, check lien waivers

Phase 9: Specialty Estimate Types

Renovation/Remodel Estimating

Add these factors to renovation estimates:

  • Selective demolition: Price item-by-item (never lump sum)
  • Hazmat survey: Asbestos ($3-5K), lead paint ($2-4K) — MANDATORY before bid
  • Abatement: 2-5x removal cost vs new construction equivalent
  • Protection of existing: Dust barriers, floor protection, HVAC isolation
  • Working hours: Occupied buildings = nights/weekends = premium labor
  • Discovery allowance: 10-15% for hidden conditions behind walls
  • Temporary facilities: HVAC, power, restrooms during renovation
  • Phasing/sequencing: Adds 15-30% management overhead
Sitework Estimating

Critical factors:

yaml
sitework_checklist:
  geotechnical:
    - Soil bearing capacity
    - Water table depth  
    - Rock depth (blasting vs mechanical?)
    - Contamination (Phase I/II ESA results)
    
  earthwork:
    cut_cy: 0
    fill_cy: 0
    import_export: 0    # Net CY to haul
    haul_distance_miles: 0
    compaction_required: standard | proctor_95 | proctor_98
    
  utilities:
    water_tap_fee: 0
    sewer_tap_fee: 0
    fire_line: 0
    storm_detention: required | not_required
    
  paving:
    asphalt_sy: 0
    concrete_sy: 0
    curb_lf: 0
    striping_lf: 0
    
  landscape:
    sod_sf: 0
    trees_ea: 0
    irrigation: yes | no
    erosion_control: silt_fence | inlet_protection | retention_pond
MEP (Mechanical/Electrical/Plumbing) Quick Checks
System$/SF Benchmark (Commercial Office)Flag If
HVAC$25-$50/SF>$55 or <$20
Plumbing$12-$25/SF>$30 or <$8
Fire Protection$4-$8/SF>$10 or <$3
Electrical (power)$18-$35/SF>$40 or <$12
Low voltage/data$5-$12/SF>$15 or <$3
Total MEP$64-$130/SF>$150 or <$46

Phase 10: Escalation & Location Adjustments

Construction Cost Escalation
Future Cost = Current Cost × (1 + Annual Rate) ^ (Months to Midpoint ÷ 12)

Recent escalation trends (US):

  • 2020-2022: 8-15% annually (pandemic/supply chain)
  • 2023-2024: 4-6% annually (normalizing)
  • 2025-2026 forecast: 3-5% annually
  • Long-term average: 3-4% annually

Always escalate to the MIDPOINT of construction, not the start.

Location Factor Application
Local Cost = National Average Cost × City Cost Index

Sample RSMeans City Cost Indices (100 = national average):

CityIndexCityIndex
New York, NY130-145Dallas, TX88-95
San Francisco, CA125-140Atlanta, GA90-97
Boston, MA115-130Phoenix, AZ88-94
Chicago, IL110-120Denver, CO95-105
Seattle, WA108-118Nashville, TN88-95
Washington, DC100-110Charlotte, NC85-92
Miami, FL92-100Houston, TX85-93
Minneapolis, MN105-112Rural areas70-85

Phase 11: Estimate Quality Review

100-Point Estimate Quality Rubric
DimensionWeightCriteria
Scope completeness20All spec sections priced, no gaps, exclusions documented
Quantity accuracy20QTO verified, cross-checks pass, waste factors applied
Pricing basis153+ sub quotes per trade, current material prices, documented sources
Indirect costs10GCs detailed (not lump), schedule-based items tied to duration
Markup appropriateness10Market-competitive, risk-adjusted, contingency justified
Documentation10Assumptions listed, basis of estimate narrative, organized by division
Adjustments10Location factor applied, escalation to midpoint, seasonal factors
Presentation5Professional format, clear summary, alternates separated

Grading: 90+ = Bid-ready | 75-89 = Needs refinement | 60-74 = Major gaps | <60 = Redo

Peer Review Checklist
  • All addenda acknowledged and incorporated?
  • Spec sections cross-referenced to QTO? (no orphan specs)
  • Sub quotes match scope of work? (read exclusions!)
  • General conditions duration matches schedule?
  • Bond premium calculated on TOTAL including markups?
  • Sales tax applied correctly? (varies by state, some exempt)
  • Prevailing wage rates used if required? (Davis-Bacon, state)
  • Owner-furnished items excluded from pricing?
  • Alternates priced separately and clearly?
  • Math checked independently? (not just formula check — spot-check quantities)

Phase 12: Common Mistakes & Edge Cases

10 Estimate-Killing Mistakes
#MistakePrevention
1Missing addendaChecklist: log every addendum, initial when incorporated
2Incomplete sub scopeWrite scope sheets with inclusions AND exclusions
3Wrong labor ratesVerify union vs open shop, prevailing wage, location
4No escalationALWAYS escalate to construction midpoint
5Lump sum general conditionsDetail every line item tied to schedule
6Ignoring phasingMulti-phase = mobilize/demobilize multiple times
7Missing temporary workShoring, dewatering, winter protection, dust control
8Under-priced site conditionsGet geotech report BEFORE estimating foundations
9Scope gaps between tradesWho installs the backing for the TV mount?
10Not reading the fine printLiquidated damages, retainage, payment terms
Edge Cases

Occupied building renovation:

  • Work hours restriction → labor premium 15-40%
  • Dust/noise control → add $2-5/SF
  • Security/escort requirements → add supervision cost
  • Existing condition discovery → 10-15% allowance minimum

Remote/rural project:

  • Travel/per diem for crews → $150-$250/worker/day
  • Material delivery premium → 5-15% depending on distance
  • Limited sub market → fewer quotes, less competitive pricing
  • Equipment mobilization → long haul costs for cranes, excavators

Fast-track schedule:

  • Overtime premium → plan 20-30% labor cost increase
  • Acceleration costs → additional supervision, equipment
  • Out-of-sequence work → productivity losses 10-25%
  • Premium material delivery → expediting fees

Public/government work:

  • Prevailing wages → 20-40% labor cost increase
  • DBE/MBE/WBE goals → subcontracting requirements, good faith effort
  • Buy American/Buy America → material cost premium 10-30%
  • Bid protest risk → ensure perfect compliance with ITB

Design-Build:

  • Design contingency higher (incomplete docs at pricing)
  • Self-perform vs sub trade-offs
  • Design liability insurance (professional liability)
  • Allowances for owner decisions not yet made

Natural Language Commands

CommandAction
"Estimate this project"Run full estimate workflow from Phase 1
"Price [division/trade]"Develop unit costs for specific trade
"Check my quantities"Run QTO verification cross-checks
"Value engineer [system]"Generate VE alternatives with savings
"Write change order for [scope]"Generate CO with pricing and backup
"Compare sub quotes for [trade]"Score and compare subcontractor bids
"Monthly cost report"Generate EVM-based cost report
"Bid/no-bid analysis for [project]"Run decision scorecard
"Location adjust to [city]"Apply RSMeans location factor
"Escalate costs to [date]"Calculate escalation to future midpoint
"Review my estimate"Run 100-point quality rubric
"Generate bid summary"Format estimate for bid submission

© LeoYeAI, MIT. Rendered from Markdown: HTML in the file is shown as text, images as links, and headings moved down two levels. Raw file

Files

SKILL.md and 2 other files in skills/afrexai-construction-estimator of LeoYeAI/openclaw-master-skills.

  • SKILL.md
  • README.md
  • _meta.json

Open the folder on GitHubat commit e5199b5

Compare with similar skills

Afrexai Construction Estimator next to the 5 skills that share the most tags, products or categories with it. Stars are the repository's; “used in” counts other GitHub owners with a copy.

Afrexai Construction Estimator compared with similar skills
SkillStarsUsed inTokensAuto-checkLicenceRepo updated
Afrexai Construction Estimator this skillLeoYeAI/openclaw-master-skills2.2k—~6.1kAutomated safety check: PassMIT
Doc Coauthoringaws-samples/sample-strands-agent-with-agentcore19540 repos~3.2kAutomated safety check: PassMIT
Amazon Buy Box Monitorbrowser-act/skills6.1k1 repos~1.6kAutomated safety check: PassMIT
Tourmind Bookingtourmind-com/Tourmind-Booking-Skills1.8k—~13kAutomated safety check: PassMIT
Audit Onboarding Proposalhoangnb24/repository-harness1.2k—~4kAutomated safety check: PassMIT
No Negative EchoLB623/no-negative-echo900—~965Automated safety check: PassMIT

Similar skills

  • Doc Coauthoring

    aws-samples/sample-strands-agent-with-agentcore

    Official

    Guide users through a structured workflow for co-authoring documentation.

    195 GitHub starsUsed in 40 repos~3.2k tokens
    Sales & SupportAuto-check passed
  • Amazon Buy Box Monitor

    browser-act/skills

    Pulls Amazon product details, competing seller prices and seller ratings for a given ASIN through the BrowserAct API, without browser automation.

    6.1k GitHub starsUsed in 1 repo~1.6k tokens
    Sales & SupportAuto-check passed
  • Tourmind Booking

    tourmind-com/Tourmind-Booking-Skills

    MUST USE for any hotel or accommodation intent in any language, including hotel search, hotel recommendations, nearby accommodation, hostels, guesthouses, resorts, where-to-stay questions, room…

    1.8k GitHub stars~13k tokensUpdated yesterday
    Sales & SupportAuto-check passed
  • Audit Onboarding Proposal

    hoangnb24/repository-harness

    Use only when the user explicitly invokes $audit-onboarding-proposal.

    1.2k GitHub stars~4k tokensUpdated 6 days ago
    Sales & SupportAuto-check passed
  • No Negative Echo

    LB623/no-negative-echo

    Prevent 此地无银三百两式 residue: finalize artifacts without echoing rejected session-only alternatives into labels, metadata, commits, PRs, or handoffs.

    900 GitHub stars~965 tokensUpdated 1 mo ago
    Sales & SupportAuto-check passed
  • GEO Service Proposal Generator

    zubair-trabzada/geo-seo-claude

    Builds a client-ready AI-search-optimization proposal from an existing GEO audit, with pricing tiers, an ROI estimate and a markdown document ready to send.

    11k GitHub stars~3k tokensUpdated today
    Sales & SupportAuto-check: notes

More from LeoYeAI/openclaw-master-skills

All 1,235 skills in this repo
  • DevOps Pipeline Management

    LeoYeAI/openclaw-master-skills

    Manages pipelines on a DevOps quality and efficiency platform through its OpenAPI: list workspaces and templates, create, update, run and cancel pipelines, and read run records.

    2.2k GitHub stars~4.2k tokensUpdated 2 mo ago
    Auto-check: notes
  • Feishu Document Collaboration

    LeoYeAI/openclaw-master-skills

    Patches OpenClaw's Feishu extension so an edited document triggers an isolated agent session that reads the doc and replies inline, turning it into a live chat space.

    2.2k GitHub stars~2k tokensUpdated 2 mo ago
    Auto-check passed
  • Files Memory System

    LeoYeAI/openclaw-master-skills

    Multi-context memory management system for OpenClaw agents with group-isolated storage, global shared memory, workspace organization, and group-specific skills isolation.

    2.2k GitHub stars~3.8k tokensUpdated 2 mo ago
    Auto-check passed
  • GEO-Claw AI Visibility Agent

    LeoYeAI/openclaw-master-skills

    Runs a brand's AI-search visibility work end to end: diagnosing how AI platforms represent it, repositioning it, producing AI-optimized content and monitoring ongoing mentions.

    2.2k GitHub stars~4.7k tokensUpdated 2 mo ago
    Auto-check passed
  • Google Workspace CLI

    LeoYeAI/openclaw-master-skills

    Installs and authenticates the gws CLI, then automates Gmail, Drive, Sheets, Calendar, Docs, Chat and Tasks with ready-made recipes, persona bundles and security audits.

    2.2k GitHub stars~2.6k tokensUpdated 2 mo ago
    Auto-check: notes
  • HealthFit Health Advisors

    LeoYeAI/openclaw-master-skills

    Runs four advisor roles, a fitness coach, nutritionist, data analyst and TCM practitioner, to build a health profile and track workouts, diet and wellness over time.

    2.2k GitHub stars~4.4k tokensUpdated 2 mo ago
    Auto-check passed

Categories

Questions about Afrexai Construction Estimator

What does Afrexai Construction Estimator do?

Complete construction estimating and cost management system. Afrexai Construction Estimator is an agent skill from LeoYeAI/openclaw-master-skills. Complete construction estimating and cost management system.

When should I use Afrexai Construction Estimator?

Afrexai Construction Estimator fits situations like: preparing project estimates; cost breakdowns; value engineering; change order management.

How do I install Afrexai Construction Estimator in Claude Code?

Run `npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator -a claude-code`. Or copy the skill folder (skills/afrexai-construction-estimator in LeoYeAI/openclaw-master-skills) into .claude/skills/afrexai-construction-estimator in your project. Claude Code loads it when a task matches its description.

How do I install Afrexai Construction Estimator in Codex?

Run `npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator -a codex`. Or copy the skill folder (skills/afrexai-construction-estimator in LeoYeAI/openclaw-master-skills) into .agents/skills/afrexai-construction-estimator in your project. Codex loads it when a task matches its description.

Can I use Afrexai Construction Estimator in Cursor, Gemini CLI or GitHub Copilot?

Cursor, Gemini CLI, GitHub Copilot and OpenCode also load SKILL.md folders. With the skills CLI, run `npx skills add LeoYeAI/openclaw-master-skills --skill afrexai-construction-estimator -a cursor` (or -a gemini-cli, github-copilot or opencode for the others). To copy it by hand, put the folder in .cursor/skills/afrexai-construction-estimator, .gemini/skills/afrexai-construction-estimator, .github/skills/afrexai-construction-estimator and .opencode/skills/afrexai-construction-estimator in your project.

What does Afrexai Construction Estimator need to run?

SKILL.md names no scripts, command-line tools or credentials: Afrexai Construction Estimator is instructions for the agent only.

Does Afrexai Construction Estimator access the network?

SKILL.md contains no URLs. Any network use would come from the scripts or tools the agent runs. This is read from the text; nothing was executed.

Is Afrexai Construction Estimator safe to install?

Our automated static check of SKILL.md found no risky patterns, such as piping downloads into a shell, reading credential files or hidden Unicode. It is not a guarantee. Review the folder before installing.

What licence does Afrexai Construction Estimator use?

Afrexai Construction Estimator is published under the MIT licence (the repository's licence). It allows redistribution, so the full SKILL.md is shown on this page.

How many tokens does Afrexai Construction Estimator use?

About 6.1k tokens (SKILL.md is roughly 24k characters). Agents keep only the skill's name and description in context until a task matches; then they load SKILL.md in full.

What are the alternatives to Afrexai Construction Estimator?

Skills that share tags, products or a category with Afrexai Construction Estimator: Doc Coauthoring (aws-samples/sample-strands-agent-with-agentcore, 195 stars), Amazon Buy Box Monitor (browser-act/skills, 6.1k stars), Tourmind Booking (tourmind-com/Tourmind-Booking-Skills, 1.8k stars) and Audit Onboarding Proposal (hoangnb24/repository-harness, 1.2k stars). The comparison table on this page puts their stars, adoption, token cost, safety result and licence side by side.

Who maintains Afrexai Construction Estimator?

LeoYeAI (a GitHub user) maintains it in LeoYeAI/openclaw-master-skills, which has 2,161 GitHub stars. The repository holds 1,235 skills in this directory. The repository was last updated on July 20, 2026.

Source: LeoYeAI/openclaw-master-skills on GitHub. Facts on this page come from the repository at the commit we read; the author's words are quoted as theirs.